Tapa Mill: one 4 MWh battery covers peaks on two grid connections.

Battery container and four inverters under a shelter at an industrial site beside a railway Battery · 640 kW / 4 MWh

At a glance.

Wood-processing company Tapa Mill has two grid connection points, each with its own solar plant. Instead of two batteries, Nordess installed one 640 kW / 4 MWh battery whose four inverters are split between the two connections. Since April 2026 it reduces peak loads on both.

Client
Tapa Mill
Location
North-eastern Estonia
Segment
Business & industry
Battery power
640 kW
Storage capacity
4 MWh
Storage duration
6.3 h capacity ÷ power
Connected to
Two grid connections, each with solar
Earns on
Peak shaving
Commissioned
April 2026
Grid connections
Two, served by one battery
Inverters
Four, two per connection
Dot map of Finland and the Baltic states with project regions pinnedNorth-eastern Estonia

From challenge
to result.

Battery container and four inverters under a shelter at an industrial site beside a railway Battery · 640 kW / 4 MWh
  1. Challenge

    Tapa Mill is a wood-processing company in north-eastern Estonia.

    The site has two grid connection points, each with its own solar plant. The goal was to reduce peak loads on both connections.

  2. Solution

    Nordess supplied one 640 kW / 4 MWh battery, commissioned in April 2026.

    The battery's four inverters are split between the two connection points, so one battery covers the peaks of both connections.

  3. Results

    • Running since April 2026.
    • One battery reduces peak loads on both grid connections.
    • Results have not been published yet.

How the battery is connected.

One battery with four inverters serves both of the site's grid connections, two inverters on each. Each connection also has its own solar plant.

Battery640 kW / 4 MWhDC/ACDC/ACDC/ACDC/ACInvertersGrid connection 1Grid connection 2GridSolar plantGridSolar plantSite loadSite loadBattery640 kW / 4 MWhDC/ACDC/ACDC/ACDC/ACInvertersGrid connection 1GridSolar plantSite loadGrid connection 2GridSolar plantSite load
Simplified diagram.

About this project.

Can one battery serve two grid connections?

Yes. At Tapa Mill the battery's four inverters are split between the two connection points, two on each, so one battery covers the peaks of both.

What is the battery used for?

To reduce peak loads on the site's two grid connections.

How big is the system?

640 kW / 4 MWh. It stores more than six hours of its own power.

When did it start running?

In April 2026.